Construction Areas

Overview and Schedule

View the construction overview and schedule graphic. [6.3 MB pdf]

Schedule and Map Overview

Construction Areas Breakdown

Western Section

Western Section

Dark Green: Mid-2009-Early 2011
Light Green: Early 2011-Late 2012 (Site preparation in late 2010)

Major Activities/Impacts
  • Work will occur near Rod Road, Storey Avenue, Ruckman Avenue and Armistead Road neighborhoods
  • Tree removal, clearing, grubbing and grading (site preparation)
  • Visual impacts
  • Extended concrete pours
  • Night work for traffic tie-ins
  • Loss of parking (10 spaces at Rod Road)

Battery Tunnel and Approaches

Battery Tunnel and Approaches

Yellow: Late 2009-Early 2011
Light Blue: Early 2011-Late 2012

Major Activities/Impacts
  • Work will occur near Riley Ave. (residential neighborhood)
  • Closure of Lincoln Boulevard (near the National Cemetery)
  • Deep soil excavation
  • Concrete pours
  • Stockpiling and hauling of material

Eastern Section

Eastern Section

Dark Blue: Late 2010-Late 2012
Orange:
Temporary Detour
Construction: Early 2010-Early 2011
Traffic on Detour: Early 2011-Late 2012

Major Activities/Impacts
  • Building demolition (Public Storage)
  • Halleck St. and Marshall Ave. closures (Mason Street to Gorgas Avenue)
  • Pedestrian access restricted (north-south connection from Richardson Boulevard or McDowell Avenue
  • Loss of parking
  • Visual impact