Construction Areas
Overview and Schedule
View the construction overview and schedule graphic. [6.3 MB pdf]

Construction Areas Breakdown
Western Section

Dark Green: Mid-2009-Early 2011
Light Green: Early 2011-Late 2012 (Site preparation in late 2010)
Major Activities/Impacts
- Work will occur near Rod Road, Storey Avenue, Ruckman Avenue and Armistead Road neighborhoods
- Tree removal, clearing, grubbing and grading (site preparation)
- Visual impacts
- Extended concrete pours
- Night work for traffic tie-ins
- Loss of parking (10 spaces at Rod Road)
Battery Tunnel and Approaches

Yellow: Late 2009-Early 2011
Light Blue: Early 2011-Late 2012
Major Activities/Impacts
- Work will occur near Riley Ave. (residential neighborhood)
- Closure of Lincoln Boulevard (near the National Cemetery)
- Deep soil excavation
- Concrete pours
- Stockpiling and hauling of material
Eastern Section

Dark Blue: Late 2010-Late 2012
Orange:
Temporary Detour
Construction: Early 2010-Early 2011
Traffic on Detour: Early 2011-Late 2012
Major Activities/Impacts
- Building demolition (Public Storage)
- Halleck St. and Marshall Ave. closures (Mason Street to Gorgas Avenue)
- Pedestrian access restricted (north-south connection from Richardson Boulevard or McDowell Avenue
- Loss of parking
- Visual impact