Construction Contract Information

Contract Details

The Doyle Drive Replacement Project has been divided into eight contracts.

View an Overview of the Construction Contracts

 Contract #1

Scope of Work:
The Environmental Mitigation contract has been divided into five parts as listed below.

Contract Prime Contractor
Amt.
Plant Collection, Salvaging and Propagation
Hanford $0.6M
Historic Building Stabilization Centric Construction $2.0M
Tree Program Professional Tree Care Co.
$3.0M
Advanced Geotechnical Work Malcolm Drilling $0.5M
Wetland Mitigation TBD $2.8M

Status:
Plant Collection, Salvaging and Propagation, Tree Program & Historic Building Stabilization contracts have been awarded and are in progress.

View a Fact Sheet for Contract #1 [70 KB pdf]

 Contract #2

Scope of Work:
Utility Relocation

Prime Contractor: Ghilotti Bros., Inc.
Contract Amount:   $19.0M

Status:
Contract has been awarded and work is in progress.

View a Fact Sheet for Contract #2 [1.72 MB pdf]
View the Utility Relocations Map [2.65 MB pdf]

 Contract #3

Scope of Work:
Permanent Roadway Section, Southbound High Viaduct, Southern Park Presidio Interchange, Ruckman Undercrossing

Prime Contractor: C.C. Meyers

Status:
Work is in progress. Construction began December 2009.

View a map of Contract #3 [3.8 MB pdf]

 Contract #4

Scope of Work:
At-Grade Detour, Southbound Battery Tunnel, Permanent Roadway Section, Electrical and Mechanical Substation, Retaining Walls, Traffic Switch

Status:
Bid documents were opened February 26, 2010. Contract award anticipated in March 2010.

Click here for more details.
View a Fact Sheet for Contract #4 [465 KB pdf]
View a map of Contract #4
[3.8 MB pdf]

 Contract #5

Scope of Work:
Main Post Tunnels, Northbound Battery Tunnel, Demolish Existing Low Viaduct, Electrical and Mechanical Substation, Traffic Switch

Status:
Bid Documents Anticipated Fall 2010

View a map of Contract #5 [3.9 MB pdf]

 Contract #6

Scope of Work:
Girard Road Undercrossing, Low Viaduct

Status:
Bid Documents Anticipated Spring 2011

View a map of Contract #6 [3.9 MB pdf]

 Contract #7

Scope of Work:
Northbound High Viaduct, Northern Park Presidio Interchange, Northbound Roadway to Merchant Road, Demolish Existing High Viaduct

Status:
Bid Documents Anticipated Spring 2011

View a map of Contract #7 [3.8 MB pdf]

 Contract #8

Scope of Work:
Landscaping

Status:
Anticipated 2013
*Landscaping will commence upon completion of construction.

View a map of Contract #8 [3.8 MB pdf]