PHASE I: December 2009 - Spring 2012

Phase I was completed on April 30, 2012 when Doyle Drive traffic was transferred onto a temporary bypass and the completed southbound structures.

PHASE II: 2012 - 2015

Traffic Transferred onto a Temporary Bypass

In April 2012, traffic was shifted onto a bypass next to Doyle Drive with five lanes - wider than those on the existing Doyle Drive - and with opposing traffic separated by a median barrier.

Two Highway 1 ramps are closed: NB Doyle Drive to SB Park Presidio/Hwy 1 and NB Park Presidio/Hwy 1 to SB Doyle Drive. See details about the ramp closures.

Weekend Closure of Doyle Drive

In 2015 there will be a weekend closure of Doyle Drive to transfer traffic from the temporary bypass onto the final Presidio Parkway.

 

FINAL ALIGNMENT: 2015

Traffic on the Final Presidio Parkway

In 2015, major construction will be complete and traffic will be on the final Presidio Parkway. Final project activities after this will include removal of the temporary detour and landscaping.

 

 